January 2006 update


Dear all,

Happy New Year. I hope you all had a good Christmas.

To update you since my last update on 23rd December 2005:

  1. Manolo has been making all necessary visits to site to check steelwork and answer any queries whilst I have been away.
  2. Progress on structures:

Block A

(4F) is now 100% complete with the third floor slab complete to both halves.

Block B (4J) is also now 100% complete with the third floor slab complete to both halves.

Block C (4G) is now approximately 60% complete, with the second floor slab cast, the retaining wall completed up to the lift shaft and half the columns resting on the foundations cast.

Block D (4K) is now 70% complete, with the first half of the block complete and the street level floor slab cast in the second half.

  1. Blockwork walls to divide apartment from apartment and also define individual rooms is still progressing well  with approximately 40% of Block A complete, 40% of Block B and 30% of Block D complete. Lintels over doorways and timber door linings have been fitted to apartment walls to the first half of Block A (4F)

  1. Various flights of stairs cast to Block B (4J)
  2. The blockwork to divide up Chris Neary's apartment has now been built up as per the original plans and not to his proposal. I don't know whether or not this will give you any problems? Please let me know if we can continue to proceed with the original plan.

Attached photos show Block D (1437) and Block A (1425). 

Regards,

Philip Wright
Project Manager
Taurus Project SL

 

 