Dear all,

To briefly update you:

 

 

Second half of first floor level floor flab to Block A Remaining sections of street level and first floor level floor slabs to Block B above entrance to basement parking Columns up to street level to second half of block D

Blockwork walls to Blocks A and B have continued to be built up to separate
apartment from apartment and also to divide the living space within each
apartment.

Excavation works have been started for swimming pool no.6 between blocks C
and D.

Banks own valuer has been to site to confirm value of works complete and
hopefully approve Certificate 4.

Attached photos taken today of Block B (ref 227) and Block A (ref 231).