March Progress Report


Dear all,

 

March has seen a lot of progress on El Barranco Resort with over 100 workers on site each day.

    1.   External painting of Blocks A and B has commenced and all apartments in these two blocks now have either two or three coats of paint.

  1. The timber pergola structures above each terrace have been put in place to all 4 main blocks as well as to the 7 link villas. Further intermediate horizontal timbers will be put in place once the tower cranes have finished placing materials on individual terraces.
  2. To roadside elevations the timber walkway structures complete with overhead pergolas have been completed to all four main blocks. The decking boards are progressively being fixed in place.
  3. All floor tiling to the four main blocks and each apartment terrace has been completed.
  4. Internal decoration is progressing well.
  5. Washbasins, bidets and toilets have been placed and plumbed in in all four main blocks.
  6. Kitchen units (flat pack) have been placed in Block A and B apartments and are in the process of being assembled.
  7. Wardrobes have been placed in apartments of Block B and are presently being assembled and put into position.
  8. Internal doors are presently being fitted within Blocks A and B.
  9. All roofs have now been completed with the final tiles being fixed on the link villas this month.
  10. Since the good progress was made with Swimming Pool 1 last month work on Pools 3, 4, 5 and 6 has been even faster. Pool 3 (children’s) is complete apart from tiling. Pools 4, 5 and 6 have been excavated. The walls and base of Pool 6 have been sprayed with concrete and Pools 4 and 5 are presently being prepared for spraying of concrete.

 

 

 

 

------------------------------------ End of March report ----------------------------------