Blog

Posted By: 
Posted On: 24 November 2006

Works progress update - 24 November 2006


Dear all,

Since my last update progress on site has been made on the following items:

    1. Passageways and the terraces have been screeded to Block B, with a waterproofing latex compound being spread over approximately half of these ready to accept terrace tiles.
    2. Terrace tiling has been commenced to penthouse B302 today
    3. External rendering has continued to all blocks
    4. The first floor level timber walkway structure which will support the timber boardwalk has been fixed in place to Block B together with the timber pergola structure above.
    5. The first lift is now in place to the end of Block B nearest to The Bridge and work has commenced on installation of the second lift within the same block.
    6. Plastering of walls and ceilings to the Villas and apartments within Block C has continued
    7. Further windows have been put in place to Block , whilst all are in place in Block B.

 

The photographs below show a view of Block B taken from the road, Block A and Block B again with the lift doors evident within the shaft, the timber joists at first floor level which will support the timber boarded walkway and the timber pergola structure above.

 

Regards,    Phil

^top^


News Updates
New Road Links
Marina Nears Completion
Building Concessions
 
The Complex
Amarilla Golf Club.
14000 square metres
Complex1
Complex2