Update and site photos 13th November 2006


Dear all,

 

Since my last update progress on site has been good:

    1. Screeding of the floors to the roof-top terraces and main terraces to the penthouses to Block B has started.
    2. Further roofing works have been carried out to Blocks C and D.
    3. Further installation of ceilings has been carried out to Blocks A and C.
    4. Further external rendering of Block B (roadside elevation) and Block A (poolside elevation) has been carried out.
    5. Further general site drainage has been installed.
    6. The remaining section of stone faced wall has been built up in front of Villas 12 and 13.
    7. Plastering of the individual Villas is continuing.

The photographs below show: a general view of Block B, Block B pergola fixed in place, rendering progressing of the poolside elevation of Block A, and a general view looking down the site showing Blocks A and C (note the circular staircases in place on Block A).

Regards,   Phil