Posted By: Philip Wright
Posted On: 25 October 2006
Update 20th October 2006
Dear all,
Since my last update on progress has been made on the following items:
- Chris and other members of the Your Place Abroad sales team were on site throughout Wednesday bringing themselves and clients up to date with progress on site.
- Progress on site over the past week:
- Further roof timbering works have been carried out to Blocks A and D.
- Rendering of external walls to Blocks A and B has continued
- Screeding of floors followed by tiling has continued to to the apartments of Block B.
- Tiling of bathrooms to Villas 4,5,6 and 7 Has been completed.
- Tiling of kitchens to Villas 11 to 15 is progressing.
- The water distribution pipework has been partially laid in a ring within the site.
- The walls dividing and enclosing the gardens of Villas 3 to 10 are being built up.
- The stone dividing walls between the gardens of Villas 11 to 15 are being built.
Regards, Phil

Photo 3038 showing Block B

Photo 3044 showing Block A

Photo 3041 shoing the damp proofing membrane as applied over the screed to the terrace area to Apartment B101.