Posted By: Latest Update August 29th 2006
Posted On: 05 September 2006
Latest Update 29th August 2006
Since the last update on 25th August progress has been made on the following items:
- Regular progress meeting took place on Tuesday 29th August.
- The bank´s valuer had his usual monthly site visit yesterday to view the progress of the works and approve the value of the last certificate.
- Progress on site this week:
- All the individual villas (numbers 2 to 7 and 10) have now had their roofs tiles.
- The timber roof structure to Block B is now complete and the remaining over boarding is being carried out.
- More external rendering has been carried out to Block A.
- Installation of plaster boarded ceilings finished with a skim coat of plaster is progressing well within Block B apartments.
- Plastering of walls to Block B apartments is also progressing well.
- The staircase between Block D and Villa 8 has been cast.
- Grouting of tiles to kitchens and bathrooms is mostly complete to Blocks B and D.
- The steelwork to support the first floor walkway and second floor pergola, roadside has been completed to blocks B and D and is almost complete to Blocks A and C.

Block B second floor apartment B301 with timber roof structure in place.

Block A second floor apartments with external walls render coated.

Block B street elevation timber covered walkway to second floor

Ground floor Block B apartment B101 with plaster finish to walls and ceilings
^top^
|