Posted By: Latest Update 25th August 2006
Posted On: 29 August 2006
Latest Update 25th August 2006
Taurus Project Manager Philip Wright Reports:
Progress has been made on the following items:
Progress on site since 4th August:
-
- The roofs of five individual villas have now been tiled inclusive of laying of ridge and hip tiles.
- The timber roof structure to Block B has been put in place and over-boarding is presently ongoing prior to fixing of tiles.
- Rendering of the external walls of Villas 1 to 7 and 10 has been carried out.
- Rendering of the external walls to second floor apartments to the first half of Block B has been carried out with rendering of the walls to the second floor apartments to Block A presently being carried out.
- Plastering of the walls and ceilings to the basement parking areas of Blocks A and C is almost complete.
- The staircases between the Terrace bar and Block A and between Block C and Villa 11 have been cast.
- Two sections of retaining walls have been cast, one adjacent to the underground water storage tank, the other between Villas 3 and 4 ready for a staircase to be built up against it.
- Plastering of apartment walls and ceilings is progress to Block B.
- Tiling of kitchens and bath/shower rooms is almost complete within the apartments of Blocks B and D.
- External electrical lighting points are being chased out for and conduits installed ready for wiring.
- The timber covered walkway to the second floor to Block B under the boarded roof covering is now looking very impressive and is softening the harsh lines of the concrete.


The covered walkway to Block B

Plastered walls and ceiling to a Blcok B apartment

Block B roadside

Villa 10