Posted By: Latest update July 21st 2006
Posted On: 24 July 2006
Latest Update 21st July 2006
Taurus Project Manager Phillip Wright reports:

a view of the roof structures to the Villas
- Regular progress meeting took place on Tuesday
- Progress on site over week:
- Timber roof structures to Villas 2, 3, 4, 5 and 6 have been completed in preparation for fixing of clay tiles.
- Stone walls are continuing to be built up below Villas 5, 6 and 7.
- The concrete to the upper section of the ramped pedestrian walkway, which passes in front of Villas 2 and 3 has been cast in concrete.
- More apartments within Block B have been cabled.
- Further sections of basement parking floor slabs have been laid to Block C.
- Movement joints have been cut into the basement floor slabs to Blocks B and C.
- The floor to the basement storerooms has been cast to Block A in preparation for the building up in blockwork of the walls to enclose each store.
- Plumbing work has been carried out to connect each of the apartments within Block B to the main supply network.
- Ventilation stacks are being built up on the roof of Block B which will vent bathrooms.
- Plastering of apartment walls has commenced to second floor apartments to Block B.
- Rendering of external walls of the Villas has commenced with work progressing to Villas 2 and 3.

Villa 4

the progression of rendering to Villa 2