Posted By: Latest Updates 16th June 2006
Posted On: 19 June 2006
Latest Updates 16th June 2006
img 1909
Another update as of the 16th June has arrived in from Taurus Project Manager Philip Wright as follows;
- Progress on site over the week:
- Further foundations for the roadside boundary walls and for the posts, which support the pergola structures, have been cast to block C.
- The walls to the upper level of Block C have been capped with reinforced concrete.
- The foul drainage pipework has been laid and the concrete floors have been cast within Villas 1 to 5. Internal room dividing walls have been built up to Villa 2 and blockwork has commenced in Villa 3.
- The positions of the air conditioning units have been marked within each apartment in preparation for chasing out of blockwork and installation of pre-installation pipework and electrical supplies.
- The laying of the foul drainage pipework has commenced to Villas 11 to 15.
- The stone walls between the pools level and Villas 4 to 7 continue to be built up.
- Installation of soil and other waste pipework is continuing throughout the apartments.
- Boxing in of soil pipes is continuing throughout the apartments.
- The retaining walls to the equipment room adjacent to the underground water storage tank have been cast.
img 1908
Attached photograph 1908 shows Villa 3 with completed floor slab, 1909 shows a view of the stone walls being constructed below villas 4 to 7 and 1913 shows a general view looking up the site towards Teide.
img 1913